Background
The Ridgeline Project is a 10,000 acre data center campus proposed by Fundamental Data LLC for development in Tucker County on the site pictured above. Its first phase includes a gas and diesel power plant located between the towns of Davis and Thomas.

The West Virginia Department of Environmental Protection issued an Air Quality Permit for this power plant, without any air dispersal or environmental impact modeling. The permit allows for 30 million gallons of diesel fuel to be stored on site. The WVDEP listened to over 5 hours of comments from the community, urging them not to approve the permit.
The same day Fundamental Data applied for this permit on March 18, 2025, the WV legislature passed HB2014, a bill that prevents communities from having any say in off-grid power plant and data center developments. The bill diverts the vast majority of tax revenue away from the communities who will bear the costs of these facilities and allows data center developers to keep basic details of their projects hidden from the public.

It was over a year before representatives of Fundamental Data showed up unannounced at a Town Hall in Davis to speak with the community.
At that meeting, they announced the scale of the project: a data center campus spanning 10,000 acres including multiple power plants, a nuclear plant, and thousands of acres of solar infrastructure.
Despite the approved air quality permit and multiple public statements that the end-user of this power would be data centers, the WV Secretary of Commerce accepted Fundamental Data's claims that this project is still "conceptual." They have not applied to be a Certified Microgrid or Hyperscale Data Center campus.

.png)